(01) Berkeley Crossing

This development is part of the Township's 

state-mandated affordable housing obligation

Berkeley Crossing 4.8.19Address

663 & 665 Springfield Avenue & 88 River Road - Block 502 lot 1, 502 lot 2, 502 lot 4, 502 lot 5

Total Number of Units -(Affordable Housing)

Types of Units

Amenities

45 Rental Units (8 AH)
  • 9 one bedroom
  • 35 two bedroom
  • 1 three bedroom
88 Parking Spaces
Retail Space4,300 sq ft

Other names

Formerly known as "Berkeley Florist"

Berkeley Crossing affirmative marketing flyer Page 1[76]

Status

DateUpdated Status
February 2022
  • Site has been cleared, first permits for construction have been acquired. 
  • Elite starts marketing affordable units (see flyer here
November 2020
  • Township Council to consider adoption of financial agreement ordinance
  • Council to consider resolution approving new Redevelopment Agreement
October 2020
  • Township Council to introduce financial agreement ordinance at 10/27 meeting
July 2020
  • Township adopts Redevelopment Plan ordinance
  • Planning Board hears Redevelopment Plan amendments with revised concept plan.
June 2020
  • Ordinance introduced approving Redevelopment Plan amendments.
May 2020 
  • Council approves Resolution declaring extra adjacent Lot 3 as an area in need of redevelopment for Elite Berkeley Florist.
  • Planning Board approves resolution of same.
  • Planning Board hears Redevelopment Plan amendments
March 2020 
  • Township refers Block 502, Lot 3 to Planning Board for review as AINoR (Area in Need of Redevelopment)
Winter 2019/2020 
  • Redeveloper seeking to modify Redevelopment Project:
    • Adding Block 502, Lot 3 to Redevelopment Area; and
    • Revising Concept Plan for Redevelopment Project.
November 2019
  • Executed Financial Agreement (PILOT)
  • Executed Amendment to Redevelopment Plan
October 2019
  • Planning Board Approval
  • Resolution Compliance Pending
  • Footing and Foundation Permit Pending
  • TWA signed
  • Council Approval for PILOT
July 2019
  • Shovel in ground expected by fall/winter 2019/2020
  • The first building should be ready for occupancy approximately 12 to 18 months later. Approximately mid-2020
June 2019
  • Application approved by Planning Board
2018 
  • Area in Need of Redevelopment Designation            Block 502, Lots 1, 2, 4 & 5
  • Council adopts Redevelopment Plan & Agreement