February 2022 | - Site has been cleared, first permits for construction have been acquired.
- Elite starts marketing affordable units (see flyer here)
|
November 2020 | - Township Council to consider adoption of financial agreement ordinance
- Council to consider resolution approving new Redevelopment Agreement
|
October 2020 | - Township Council to introduce financial agreement ordinance at 10/27 meeting
|
July 2020 | - Township adopts Redevelopment Plan ordinance
- Planning Board hears Redevelopment Plan amendments with revised concept plan.
|
June 2020 | - Ordinance introduced approving Redevelopment Plan amendments.
|
May 2020 | - Council approves Resolution declaring extra adjacent Lot 3 as an area in need of redevelopment for Elite Berkeley Florist.
- Planning Board approves resolution of same.
- Planning Board hears Redevelopment Plan amendments
|
March 2020 | - Township refers Block 502, Lot 3 to Planning Board for review as AINoR (Area in Need of Redevelopment)
|
Winter 2019/2020 | - Redeveloper seeking to modify Redevelopment Project:
- Adding Block 502, Lot 3 to Redevelopment Area; and
- Revising Concept Plan for Redevelopment Project.
|
November 2019 | - Executed Financial Agreement (PILOT)
- Executed Amendment to Redevelopment Plan
|
October 2019 | - Planning Board Approval
- Resolution Compliance Pending
- Footing and Foundation Permit Pending
- TWA signed
- Council Approval for PILOT
|
July 2019 | - Shovel in ground expected by fall/winter 2019/2020
- The first building should be ready for occupancy approximately 12 to 18 months later. Approximately mid-2020
|
June 2019 | - Application approved by Planning Board
|
2018 | - Area in Need of Redevelopment Designation Block 502, Lots 1, 2, 4 & 5
- Council adopts Redevelopment Plan & Agreement
|